Schedule Change History
Stage : Combined Evaluation
| # | Edit Date | Original Schedule | Description | |
| Start | Until | |||
| 1 | September 4, 2023 11:17 | September 4, 2023 07:00 | September 4, 2023 11:00 | Consultants Selection Committee has received ADB's NOL |
| 2 | September 4, 2023 10:42 | September 4, 2023 07:00 | September 4, 2023 09:30 | Consultants Selection Committee has received ADB's NOL |
| 3 | September 4, 2023 09:22 | September 4, 2023 07:00 | September 4, 2023 12:00 | Consultants Selection Committee has received ADB's NOL |
| 4 | September 4, 2023 09:11 | September 4, 2023 07:00 | September 4, 2023 09:00 | Consultants Selection Committee has received ADB's NOL |
| 5 | September 2, 2023 06:13 | September 4, 2023 07:00 | September 4, 2023 23:59 | Consultants Selection Committee has received ADB's NOL |
| 6 | August 29, 2023 07:45 | August 29, 2023 07:00 | August 29, 2023 23:59 | Consultants Selection Committee needs time for NOL from ADB |
| 7 | August 14, 2023 13:26 | August 24, 2023 00:00 | August 24, 2023 23:59 | Consultants Selection Committee needs time for NOL from ADB |
| 8 | August 10, 2023 13:04 | August 21, 2023 00:00 | August 21, 2023 23:59 | Consultants Selection Committee needs time for NOL from ADB |
| 9 | August 1, 2023 10:23 | August 15, 2023 08:00 | August 15, 2023 23:59 | Consultants Selection Committee needs time for NOL from ADB |
| 10 | July 20, 2023 16:51 | July 26, 2023 07:00 | July 28, 2023 23:59 | Consultants Selection Committee needs time for NOL from ADB |
| 11 | May 12, 2023 17:35 | June 10, 2023 07:00 | June 10, 2023 23:59 | Consultants Selection Committee waiting for package adjusment |
| 12 | March 31, 2023 07:06 | April 10, 2023 07:00 | April 10, 2023 23:59 | Consultants Selection Committee waiting for package adjusment |
| 13 | February 16, 2023 09:14 | March 13, 2023 07:00 | March 13, 2023 23:59 | Consultants Selection Committee waiting for package adjusment |