Schedule Change History
Stage : Standstill Period
#Edit DateOriginal ScheduleDescription
StartUntil
1January 6, 2025 15:33January 7, 2025 08:00January 16, 2025 16:30pokja need additional time for contract negotiation
2December 30, 2024 09:12January 1, 2025 08:00January 10, 2025 16:30pokja need additional time for contract negotiation
3December 23, 2024 14:10December 25, 2024 08:00January 3, 2025 16:30pokja need additional time for contract negotiation
4December 16, 2024 10:22December 29, 2024 08:00October 7, 2025 16:30pokja need additional time to input financial proposal in accordance with AIIB NOL
5December 11, 2024 10:56January 1, 2025 08:00October 10, 2025 16:30(POKJA) waiting for Concurence from Ministry Public Works
6December 3, 2024 10:28December 20, 2024 08:00December 29, 2024 16:30The Procurement Committee (POKJA) waiting for Concurence from AIIB
7November 21, 2024 14:31December 10, 2024 08:00December 19, 2024 16:30The Procurement Committee (POKJA) waiting for Concurence from AIIB
8November 14, 2024 15:59December 7, 2024 08:00December 16, 2024 16:30The Procurement Committee (POKJA) waiting for Concurence from AIIB
9November 6, 2024 11:54December 6, 2024 08:00December 15, 2024 16:30The Procurement Committee (POKJA) waiting for Concurence from AIIB
10October 30, 2024 13:06December 6, 2024 08:00December 13, 2024 16:30The Procurement Committee (POKJA) waiting for Concurence from AIIB
11October 17, 2024 10:13November 23, 2024 08:00December 2, 2024 16:30The Procurement Committee (POKJA) has received Concurence from AIIB