Schedule Change History
Stage : Contract Signing
#Edit DateOriginal ScheduleDescription
StartUntil
1January 6, 2025 15:33January 27, 2025 08:00January 27, 2025 16:30pokja need additional time to input financial proposal in accordance with AIIB NOL
2December 30, 2024 09:12January 21, 2025 08:00January 21, 2025 16:30pokja need additional time to input financial proposal in accordance with AIIB NOL
3December 23, 2024 14:10January 13, 2025 08:00January 13, 2025 16:30pokja need additional time to input financial proposal in accordance with AIIB NOL
4December 16, 2024 10:22January 16, 2025 08:00January 16, 2025 16:30pokja need additional time to input financial proposal in accordance with AIIB NOL
5December 11, 2024 10:56January 21, 2025 08:00January 21, 2025 16:30(POKJA) waiting for Concurence from Ministry Public Works
6December 3, 2024 10:28January 7, 2025 08:00January 7, 2025 16:30The Procurement Committee (POKJA) waiting for Concurence from AIIB
7November 21, 2024 14:31December 27, 2024 08:00December 27, 2024 16:30The Procurement Committee (POKJA) waiting for Concurence from AIIB
8November 14, 2024 15:59December 24, 2024 08:00December 24, 2024 16:30The Procurement Committee (POKJA) waiting for Concurence from AIIB
9November 6, 2024 11:54December 27, 2024 08:00December 27, 2024 16:30The Procurement Committee (POKJA) waiting for Concurence from AIIB
10October 30, 2024 13:06December 25, 2024 08:00December 25, 2024 16:30The Procurement Committee (POKJA) waiting for Concurence from AIIB
11October 17, 2024 10:13December 6, 2024 08:00December 6, 2024 16:30The Procurement Committee (POKJA) has received Concurence from AIIB