Schedule Change History
Stage : Clarification Request Period
#Edit DateOriginal ScheduleDescription
StartUntil
1September 4, 2024 14:02September 17, 2024 08:00October 3, 2024 16:30The Procurement Committee (POKJA) needs additional time for evaluation and Approval Non Objection Letter of Report EOI and RFP
2August 30, 2024 07:57September 3, 2024 08:00September 19, 2024 16:30The Procurement Committee (POKJA) needs additional time for evaluation and Approval Non Objection Letter of Report EOI and RFP
3August 16, 2024 19:21August 27, 2024 08:00September 4, 2024 16:30The Procurement Committee (POKJA) needs additional time for evaluation and Approval Non Objection Letter of Report EOI and RFP
4August 11, 2024 01:07August 20, 2024 08:00September 4, 2024 16:30The Procurement Committee (POKJA) needs additional time for evaluation and Approval Non Objection Letter of Report EOI and RFP
5July 31, 2024 10:28August 10, 2024 08:00August 23, 2024 16:30The Procurement Committee (POKJA) needs additional time for evaluation and Approval Non Objection Letter of Report EOI and RFP
6July 29, 2024 08:24July 30, 2024 08:00August 14, 2024 16:30The Procurement Committee (POKJA) needs additional time for evaluation and Approval Non Objection Letter of Report EOI and RFP
7July 12, 2024 16:38July 29, 2024 08:00August 14, 2024 16:30The Procurement Committee (POKJA) needs additional time for evaluation and Approval Non Objection Letter of Report EOI and RFP