Schedule Change History
Stage : Evaluation of Technical Proposals
| # | Edit Date | Original Schedule | Description | |
| Start | Until | |||
| 1 | January 7, 2025 14:01 | October 11, 2024 08:00 | January 13, 2025 16:30 | POKJA has received Concurence for submission 2 from IsDB |
| 2 | January 6, 2025 14:00 | October 11, 2024 08:00 | January 6, 2025 16:30 | Waiting For Concuerence from IsDB |
| 3 | December 30, 2024 09:27 | October 11, 2024 08:00 | December 30, 2024 16:30 | Waiting For Concuerence from IsDB |
| 4 | December 19, 2024 14:27 | October 11, 2024 08:00 | December 20, 2024 16:30 | Waiting For Concuerence from IsDB |
| 5 | December 11, 2024 11:17 | October 11, 2024 08:00 | December 8, 2024 16:30 | Waiting For Concuerence from IsDB |
| 6 | December 3, 2024 10:28 | October 11, 2024 08:00 | December 2, 2024 16:30 | Waiting For Concuerence from IsDB |
| 7 | November 21, 2024 11:49 | October 11, 2024 08:00 | November 18, 2024 16:30 | Waiting For Concuerence from IsDB |
| 8 | November 14, 2024 16:22 | October 11, 2024 08:00 | November 10, 2024 16:30 | Waiting For Concuerence from IsDB |
| 9 | October 30, 2024 14:07 | October 11, 2024 08:00 | October 24, 2024 16:30 | Waiting For Concuerence from IsDB |
| 10 | October 20, 2024 10:59 | October 11, 2024 08:00 | October 21, 2024 16:30 | Pokja's Still Evaluation Technical Proposal |
| 11 | September 4, 2024 14:02 | October 19, 2024 08:00 | October 30, 2024 16:30 | The Procurement Committee (POKJA) needs additional time for evaluation and Approval Non Objection Letter of Report EOI and RFP |
| 12 | August 30, 2024 07:57 | October 4, 2024 08:00 | October 21, 2024 16:30 | The Procurement Committee (POKJA) needs additional time for evaluation and Approval Non Objection Letter of Report EOI and RFP |
| 13 | August 16, 2024 19:21 | September 27, 2024 08:00 | October 10, 2024 16:30 | The Procurement Committee (POKJA) needs additional time for evaluation and Approval Non Objection Letter of Report EOI and RFP |
| 14 | August 11, 2024 01:07 | September 19, 2024 08:00 | October 1, 2024 16:30 | The Procurement Committee (POKJA) needs additional time for evaluation and Approval Non Objection Letter of Report EOI and RFP |
| 15 | July 31, 2024 10:28 | September 7, 2024 08:00 | October 1, 2024 16:30 | The Procurement Committee (POKJA) needs additional time for evaluation and Approval Non Objection Letter of Report EOI and RFP |
| 16 | July 29, 2024 08:24 | August 29, 2024 08:00 | October 7, 2024 16:30 | The Procurement Committee (POKJA) needs additional time for evaluation and Approval Non Objection Letter of Report EOI and RFP |