Schedule Change History
Stage : Evaluation of Technical Proposals
#Edit DateOriginal ScheduleDescription
StartUntil
1January 7, 2025 14:01October 11, 2024 08:00January 13, 2025 16:30POKJA has received Concurence for submission 2 from IsDB
2January 6, 2025 14:00October 11, 2024 08:00January 6, 2025 16:30Waiting For Concuerence from IsDB
3December 30, 2024 09:27October 11, 2024 08:00December 30, 2024 16:30Waiting For Concuerence from IsDB
4December 19, 2024 14:27October 11, 2024 08:00December 20, 2024 16:30Waiting For Concuerence from IsDB
5December 11, 2024 11:17October 11, 2024 08:00December 8, 2024 16:30Waiting For Concuerence from IsDB
6December 3, 2024 10:28October 11, 2024 08:00December 2, 2024 16:30Waiting For Concuerence from IsDB
7November 21, 2024 11:49October 11, 2024 08:00November 18, 2024 16:30Waiting For Concuerence from IsDB
8November 14, 2024 16:22October 11, 2024 08:00November 10, 2024 16:30Waiting For Concuerence from IsDB
9October 30, 2024 14:07October 11, 2024 08:00October 24, 2024 16:30Waiting For Concuerence from IsDB
10October 20, 2024 10:59October 11, 2024 08:00October 21, 2024 16:30Pokja's Still Evaluation Technical Proposal
11September 4, 2024 14:02October 19, 2024 08:00October 30, 2024 16:30The Procurement Committee (POKJA) needs additional time for evaluation and Approval Non Objection Letter of Report EOI and RFP
12August 30, 2024 07:57October 4, 2024 08:00October 21, 2024 16:30The Procurement Committee (POKJA) needs additional time for evaluation and Approval Non Objection Letter of Report EOI and RFP
13August 16, 2024 19:21September 27, 2024 08:00October 10, 2024 16:30The Procurement Committee (POKJA) needs additional time for evaluation and Approval Non Objection Letter of Report EOI and RFP
14August 11, 2024 01:07September 19, 2024 08:00October 1, 2024 16:30The Procurement Committee (POKJA) needs additional time for evaluation and Approval Non Objection Letter of Report EOI and RFP
15July 31, 2024 10:28September 7, 2024 08:00October 1, 2024 16:30The Procurement Committee (POKJA) needs additional time for evaluation and Approval Non Objection Letter of Report EOI and RFP
16July 29, 2024 08:24August 29, 2024 08:00October 7, 2024 16:30The Procurement Committee (POKJA) needs additional time for evaluation and Approval Non Objection Letter of Report EOI and RFP