Schedule Change History
Stage : Technical Rank Announcement
| # | Edit Date | Original Schedule | Description | |
| Start | Until | |||
| 1 | January 7, 2025 14:01 | January 14, 2025 08:00 | January 23, 2025 16:30 | POKJA has received Concurence for submission 2 from IsDB |
| 2 | January 6, 2025 14:00 | January 7, 2025 08:00 | January 16, 2025 16:30 | Waiting For Concuerence from IsDB |
| 3 | December 30, 2024 09:27 | December 31, 2024 08:00 | January 9, 2025 16:30 | Waiting For Concuerence from IsDB |
| 4 | December 19, 2024 14:27 | December 21, 2024 08:00 | December 30, 2024 16:30 | Waiting For Concuerence from IsDB |
| 5 | December 11, 2024 11:17 | December 9, 2024 08:00 | December 18, 2024 16:30 | Waiting For Concuerence from IsDB |
| 6 | December 3, 2024 10:28 | December 3, 2024 08:00 | December 12, 2024 16:30 | Waiting For Concuerence from IsDB |
| 7 | November 21, 2024 11:49 | November 19, 2024 08:00 | November 28, 2024 16:30 | Waiting For Concuerence from IsDB |
| 8 | November 14, 2024 16:22 | November 11, 2024 08:00 | November 20, 2024 16:30 | Waiting For Concuerence from IsDB |
| 9 | October 30, 2024 14:07 | October 25, 2024 08:00 | October 28, 2024 16:30 | Waiting For Concuerence from IsDB |
| 10 | October 20, 2024 10:59 | October 22, 2024 08:00 | October 28, 2024 16:30 | Pokja's Still Evaluation Technical Proposal |
| 11 | September 4, 2024 14:02 | October 31, 2024 08:00 | November 6, 2024 16:30 | The Procurement Committee (POKJA) needs additional time for evaluation and Approval Non Objection Letter of Report EOI and RFP |
| 12 | August 30, 2024 07:57 | October 22, 2024 08:00 | October 28, 2024 16:30 | The Procurement Committee (POKJA) needs additional time for evaluation and Approval Non Objection Letter of Report EOI and RFP |
| 13 | August 16, 2024 19:21 | October 11, 2024 08:00 | October 17, 2024 16:30 | The Procurement Committee (POKJA) needs additional time for evaluation and Approval Non Objection Letter of Report EOI and RFP |
| 14 | August 11, 2024 01:07 | October 2, 2024 08:00 | October 8, 2024 16:30 | The Procurement Committee (POKJA) needs additional time for evaluation and Approval Non Objection Letter of Report EOI and RFP |
| 15 | July 29, 2024 08:24 | October 8, 2024 08:00 | October 8, 2024 16:30 | The Procurement Committee (POKJA) needs additional time for evaluation and Approval Non Objection Letter of Report EOI and RFP |