Schedule Change History
Stage : Final Ranking
#Edit DateOriginal ScheduleDescription
StartUntil
1February 13, 2026 14:38February 12, 2026 20:11February 12, 2026 20:30The Selection Working Group has obtained the No Objection Letter (NOL) approval from the Bank
2February 13, 2026 10:29February 12, 2026 19:01February 12, 2026 19:59The Selection Working Group has obtained the No Objection Letter (NOL) approval from the Bank
3February 12, 2026 16:01December 15, 2025 16:00December 17, 2025 23:59The Selection Working Group has obtained the No Objection Letter (NOL) approval from the Bank
4November 28, 2025 10:56March 15, 2025 00:00April 7, 2025 23:59has received the No Objection Letter (NOL) for the TER from IsDB
5February 25, 2025 14:53January 10, 2025 00:00January 16, 2025 23:59pending IsDB approval of technical evaluation results
6November 5, 2024 15:46February 5, 2025 00:00February 18, 2025 23:59already received approval from the IsDB
7November 4, 2024 19:41September 14, 2024 00:00September 26, 2024 23:59already received approval from the IsDB