Schedule Change History
Stage : Standstill Period
#Edit DateOriginal ScheduleDescription
StartUntil
1February 13, 2026 14:38February 13, 2026 08:00March 3, 2026 16:01The Selection Working Group has obtained the No Objection Letter (NOL) approval from the Bank
2February 12, 2026 16:01December 19, 2025 00:00January 2, 2026 16:00The Selection Working Group has obtained the No Objection Letter (NOL) approval from the Bank
3November 28, 2025 10:56April 15, 2025 00:00April 29, 2025 23:59has received the No Objection Letter (NOL) for the TER from IsDB
4February 25, 2025 14:53January 23, 2025 00:00February 6, 2025 23:59pending IsDB approval of technical evaluation results
5November 5, 2024 15:46February 11, 2025 00:00February 25, 2025 23:59already received approval from the IsDB
6November 4, 2024 19:41October 10, 2024 00:00October 24, 2024 23:59already received approval from the IsDB