| 1 | February 27, 2025 13:39 | March 17, 2025 00:00 | March 21, 2025 23:59 | Loan Agreement Cancellation Process |
| 2 | February 10, 2025 14:35 | March 10, 2025 23:59 | March 14, 2025 00:00 | Loan Agreement Cancellation Process |
| 3 | December 23, 2024 13:30 | January 29, 2025 00:00 | February 2, 2025 23:59 | Additional time to align with the extended time required for the previous stage |
| 4 | November 18, 2024 12:12 | December 19, 2024 00:00 | December 23, 2024 23:59 | Additional time to align with the extended time required for the previous stage |
| 5 | October 22, 2024 16:09 | December 13, 2024 00:00 | December 17, 2024 23:59 | Additional time to align with the extended time required for the previous stage |
| 6 | October 14, 2024 09:12 | December 9, 2024 00:00 | December 15, 2024 23:59 | Additional time to align with the extended time required for the previous stage |
| 7 | September 30, 2024 21:29 | October 22, 2024 00:00 | November 4, 2024 23:59 | Additional time to align with the extended time required for the previous stage |