Schedule Change History
Stage : Contract Negotiation
| # | Edit Date | Original Schedule | Description | |
| Start | Until | |||
| 1 | April 9, 2025 13:19 | January 20, 2025 08:00 | March 27, 2025 23:59 | waiting for the further process by commitment officer |
| 2 | January 30, 2025 13:08 | January 20, 2025 08:00 | January 24, 2025 23:59 | waiting for the further process by commitment officer |
| 3 | January 14, 2025 12:24 | January 16, 2025 08:00 | January 27, 2025 23:59 | Consultants Selection Committee requires additional time for evaluation technical proposal |