| 1 | April 24, 2025 09:58 | April 25, 2025 12:01 | April 25, 2025 23:59 | waiting for addendum approval from lender |
| 2 | March 27, 2025 19:54 | April 25, 2025 15:01 | April 25, 2025 23:59 | based on a letter of objection from the lender and bidder |
| 3 | March 27, 2025 19:24 | April 26, 2025 12:01 | April 26, 2025 23:59 | based on a letter of objection from the lender and bidder |
| 4 | March 27, 2025 19:21 | April 25, 2025 12:01 | April 25, 2025 16:00 | based on a letter of objection from the lender and bidder |
| 5 | March 27, 2025 19:18 | April 25, 2025 12:02 | April 25, 2025 16:00 | based on a letter of objection from the lender and bidder |
| 6 | March 27, 2025 19:17 | April 25, 2025 12:01 | April 25, 2025 16:00 | based on a letter of objection from the lender and bidder |
| 7 | March 27, 2025 19:15 | April 8, 2025 12:01 | April 8, 2025 16:00 | based on a letter of objection from the lender and bidder |