Schedule Change History
Stage : Evaluation of Financial Proposals
#Edit DateOriginal ScheduleDescription
StartUntil
1September 29, 2025 16:57August 14, 2025 14:01September 26, 2025 22:00input evaluation result and process awarding Construction of Karian Dam-Serpong Water Conveyance System (KSCS) Project Package 1
2September 26, 2025 21:31August 14, 2025 14:01September 26, 2025 20:00input evaluation result and process awarding Construction of Karian Dam-Serpong Water Conveyance System (KSCS) Project Package 1
3September 26, 2025 18:56August 14, 2025 14:01September 26, 2025 17:00input evaluation result and process awarding Construction of Karian Dam-Serpong Water Conveyance System (KSCS) Project Package 1
4September 26, 2025 16:59August 14, 2025 14:01September 26, 2025 16:00input evaluation result and process awarding Construction of Karian Dam-Serpong Water Conveyance System (KSCS) Project Package 1
5September 26, 2025 15:23August 14, 2025 14:01September 22, 2025 08:00input evaluation result and process awarding Construction of Karian Dam-Serpong Water Conveyance System (KSCS) Project Package 1
6September 9, 2025 13:33August 14, 2025 14:01September 4, 2025 13:00Process NOL to lender Construction of Karian Dam-Serpong Water Conveyance System (KSCS) Project Package 1
7August 29, 2025 10:40August 14, 2025 14:01August 18, 2025 13:00Process NOL to lender Construction of Karian Dam-Serpong Water Conveyance System (KSCS) Project Package 1
8August 13, 2025 21:36August 14, 2025 12:01August 18, 2025 13:00Process NOL to lender Construction of Karian Dam-Serpong Water Conveyance System (KSCS) Project Package 1
9August 12, 2025 16:24August 6, 2025 16:00August 15, 2025 11:00Process NOL to lender Construction of Karian Dam-Serpong Water Conveyance System (KSCS) Project Package 1
10July 29, 2025 13:46July 26, 2025 16:00July 28, 2025 11:00Process NOL to lender Construction of Karian Dam-Serpong Water Conveyance System (KSCS) Project Package 1
11July 24, 2025 13:41July 24, 2025 16:00July 28, 2025 11:00Process NOL to lender Construction of Karian Dam-Serpong Water Conveyance System (KSCS) Project Package 1
12July 18, 2025 11:30July 18, 2025 16:00July 22, 2025 11:00Process NOL to lender Construction of Karian Dam-Serpong Water Conveyance System (KSCS) Project Package 1
13July 14, 2025 09:09July 15, 2025 16:00July 18, 2025 14:00Process NOL to lender Construction of Karian Dam-Serpong Water Conveyance System (KSCS) Project Package 1
14July 8, 2025 10:59July 8, 2025 00:00July 15, 2025 10:00Process NOL to lender Construction of Karian Dam-Serpong Water Conveyance System (KSCS) Project Package 1
15July 1, 2025 14:42June 28, 2025 00:00June 29, 2025 10:00Process NOL to lender Construction of Karian Dam-Serpong Water Conveyance System (KSCS) Project Package 1
16June 20, 2025 13:51June 21, 2025 00:00June 22, 2025 10:00Process NOL to lender Construction of Karian Dam-Serpong Water Conveyance System (KSCS) Project Package 1
17June 19, 2025 10:09June 20, 2025 00:00June 21, 2025 10:00Process NOL to lender Construction of Karian Dam-Serpong Water Conveyance System (KSCS) Project Package 1
18June 16, 2025 08:45June 17, 2025 00:00June 21, 2025 10:00Process NOL to lender Construction of Karian Dam-Serpong Water Conveyance System (KSCS) Project Package 1
19June 12, 2025 11:31June 13, 2025 00:00June 15, 2025 16:00Process NOL to lender Construction of Karian Dam-Serpong Water Conveyance System (KSCS) Project Package 1
20June 5, 2025 10:54June 6, 2025 00:00June 15, 2025 16:00Process NOL to lender Construction of Karian Dam-Serpong Water Conveyance System (KSCS) Project Package 1
21May 27, 2025 07:08June 6, 2025 16:00June 15, 2025 16:00Process NOL to lender Construction of Karian Dam-Serpong Water Conveyance System (KSCS) Project Package 1
22May 27, 2025 07:01May 28, 2025 16:01June 15, 2025 16:00Process NOL to lender Construction of Karian Dam-Serpong Water Conveyance System (KSCS) Project Package 1
23April 10, 2025 16:00May 28, 2025 16:01June 18, 2025 16:00schedule acceleration Construction of Karian Dam-Serpong Water Conveyance System (KSCS) Project Package 1