Schedule Change History
Stage : Evaluation of Financial Proposals
#Edit DateOriginal ScheduleDescription
StartUntil
1September 29, 2025 16:57August 14, 2025 14:01September 26, 2025 22:00input evaluation result and process awarding Construction of Karian Dam-Serpong Water Conveyance System (KSCS) Project Package 1
2September 26, 2025 21:31August 14, 2025 14:01September 26, 2025 20:00input evaluation result and process awarding Construction of Karian Dam-Serpong Water Conveyance System (KSCS) Project Package 1
3September 26, 2025 18:56August 14, 2025 14:01September 26, 2025 16:00input evaluation result and process awarding Construction of Karian Dam-Serpong Water Conveyance System (KSCS) Project Package 1
4September 26, 2025 15:23August 14, 2025 14:01September 4, 2025 13:00input evaluation result and process awarding Construction of Karian Dam-Serpong Water Conveyance System (KSCS) Project Package 1
5August 29, 2025 10:40August 14, 2025 14:01August 18, 2025 13:00Process NOL to lender Construction of Karian Dam-Serpong Water Conveyance System (KSCS) Project Package 2
6August 13, 2025 23:54August 14, 2025 12:01August 18, 2025 13:00Process NOL to lender Construction of Karian Dam-Serpong Water Conveyance System (KSCS) Project Package 2
7August 12, 2025 16:24August 6, 2025 16:00August 15, 2025 11:00Process NOL to lender Construction of Karian Dam-Serpong Water Conveyance System (KSCS) Project Package 2
8July 29, 2025 13:47July 26, 2025 16:00July 28, 2025 11:00Process NOL to lender Construction of Karian Dam-Serpong Water Conveyance System (KSCS) Project Package 2
9July 24, 2025 13:42July 24, 2025 16:00July 28, 2025 11:00Process NOL to lender Construction of Karian Dam-Serpong Water Conveyance System (KSCS) Project Package 2
10July 18, 2025 11:33July 18, 2025 16:00July 22, 2025 11:00Process NOL to lender Construction of Karian Dam-Serpong Water Conveyance System (KSCS) Project Package 2
11July 14, 2025 09:53July 15, 2025 16:00July 18, 2025 14:00Process NOL to lender Construction of Karian Dam-Serpong Water Conveyance System (KSCS) Project Package 2
12July 8, 2025 10:59July 8, 2025 00:00July 15, 2025 10:00Process NOL to lender Construction of Karian Dam-Serpong Water Conveyance System (KSCS) Project Package 2
13July 1, 2025 14:42June 28, 2025 00:00June 29, 2025 10:00Process NOL to lender Construction of Karian Dam-Serpong Water Conveyance System (KSCS) Project Package 2
14June 20, 2025 13:54June 21, 2025 00:00June 22, 2025 10:00Process NOL to lender Construction of Karian Dam-Serpong Water Conveyance System (KSCS) Project Package 2
15June 19, 2025 10:12June 20, 2025 00:00June 21, 2025 10:00Process NOL to lender Construction of Karian Dam-Serpong Water Conveyance System (KSCS) Project Package 2
16June 16, 2025 08:46June 17, 2025 00:00June 21, 2025 10:00Process NOL to lender Construction of Karian Dam-Serpong Water Conveyance System (KSCS) Project Package 2
17June 12, 2025 11:54June 13, 2025 00:00June 15, 2025 16:00Process NOL to lender Construction of Karian Dam-Serpong Water Conveyance System (KSCS) Project Package 2
18June 5, 2025 10:55June 6, 2025 00:00June 15, 2025 16:00Process NOL to lender Construction of Karian Dam-Serpong Water Conveyance System (KSCS) Project Package 2
19May 27, 2025 07:08June 6, 2025 16:01June 15, 2025 16:00Process NOL to lender Construction of Karian Dam-Serpong Water Conveyance System (KSCS) Project Package 2
20May 27, 2025 07:04May 28, 2025 16:01June 15, 2025 16:00Process NOL to lender Construction of Karian Dam-Serpong Water Conveyance System (KSCS) Project Package 2
21April 10, 2025 16:01May 28, 2025 16:01June 18, 2025 16:00schedule acceleration Construction of Karian Dam-Serpong Water Conveyance System (KSCS) Project Package 1