Schedule Change History
Stage : Standstill Period
| # | Edit Date | Original Schedule | Description | |
| Start | Until | |||
| 1 | September 29, 2025 17:04 | September 29, 2025 15:46 | October 14, 2025 09:00 | input evaluation result and process awarding Construction of Karian Dam-Serpong Water Conveyance System (KSCS) Project Package 1 |
| 2 | September 29, 2025 16:57 | September 26, 2025 22:26 | October 14, 2025 09:00 | input evaluation result and process awarding Construction of Karian Dam-Serpong Water Conveyance System (KSCS) Project Package 1 |
| 3 | September 26, 2025 21:31 | September 26, 2025 20:26 | October 14, 2025 09:00 | input evaluation result and process awarding Construction of Karian Dam-Serpong Water Conveyance System (KSCS) Project Package 1 |
| 4 | September 26, 2025 18:56 | September 26, 2025 16:26 | October 13, 2025 09:00 | input evaluation result and process awarding Construction of Karian Dam-Serpong Water Conveyance System (KSCS) Project Package 1 |
| 5 | September 26, 2025 15:23 | September 22, 2025 08:01 | October 9, 2025 09:00 | input evaluation result and process awarding Construction of Karian Dam-Serpong Water Conveyance System (KSCS) Project Package 1 |
| 6 | September 9, 2025 13:33 | September 5, 2025 15:46 | September 11, 2025 09:00 | Process NOL to lender Construction of Karian Dam-Serpong Water Conveyance System (KSCS) Project Package 2 |
| 7 | August 29, 2025 10:40 | August 18, 2025 15:01 | August 22, 2025 09:00 | Process NOL to lender Construction of Karian Dam-Serpong Water Conveyance System (KSCS) Project Package 2 |
| 8 | August 12, 2025 16:24 | August 15, 2025 15:01 | August 20, 2025 09:00 | Process NOL to lender Construction of Karian Dam-Serpong Water Conveyance System (KSCS) Project Package 2 |
| 9 | July 29, 2025 13:47 | July 29, 2025 09:01 | August 4, 2025 09:00 | Process NOL to lender Construction of Karian Dam-Serpong Water Conveyance System (KSCS) Project Package 2 |
| 10 | July 18, 2025 11:33 | July 25, 2025 09:01 | July 30, 2025 09:00 | Process NOL to lender Construction of Karian Dam-Serpong Water Conveyance System (KSCS) Project Package 2 |
| 11 | July 14, 2025 09:53 | July 22, 2025 09:01 | July 28, 2025 09:00 | Process NOL to lender Construction of Karian Dam-Serpong Water Conveyance System (KSCS) Project Package 2 |
| 12 | July 8, 2025 10:59 | July 15, 2025 14:01 | July 21, 2025 16:00 | Process NOL to lender Construction of Karian Dam-Serpong Water Conveyance System (KSCS) Project Package 2 |
| 13 | July 1, 2025 14:42 | June 30, 2025 14:01 | July 6, 2026 16:05 | Process NOL to lender Construction of Karian Dam-Serpong Water Conveyance System (KSCS) Project Package 2 |
| 14 | June 20, 2025 13:54 | June 23, 2025 14:01 | June 27, 2025 16:00 | Process NOL to lender Construction of Karian Dam-Serpong Water Conveyance System (KSCS) Project Package 2 |
| 15 | June 19, 2025 10:12 | June 21, 2025 14:01 | June 25, 2025 16:00 | Process NOL to lender Construction of Karian Dam-Serpong Water Conveyance System (KSCS) Project Package 2 |
| 16 | June 12, 2025 11:54 | June 17, 2025 16:01 | June 23, 2025 16:00 | schedule acceleration Construction of Karian Dam-Serpong Water Conveyance System (KSCS) Project Package 1 |
| 17 | April 10, 2025 16:01 | June 19, 2025 16:01 | June 25, 2025 16:00 | schedule acceleration Construction of Karian Dam-Serpong Water Conveyance System (KSCS) Project Package 1 |