Schedule Change History
Stage : Notification of Award
| # | Edit Date | Original Schedule | Description | |
| Start | Until | |||
| 1 | July 3, 2025 12:47 | July 17, 2025 08:01 | July 17, 2025 09:00 | Perpanjangan waktu menunggu NO dari WB |
| 2 | July 2, 2025 07:15 | July 15, 2025 08:01 | July 15, 2025 09:00 | Perpanjangan waktu menunggu NO dari WB |
| 3 | June 30, 2025 07:35 | July 14, 2025 08:01 | July 14, 2025 09:00 | Perpanjangan waktu menunggu NO dari WB |
| 4 | June 26, 2025 08:46 | July 10, 2025 16:35 | July 10, 2025 17:00 | Perpanjangan waktu menunggu NO dari WB |
| 5 | June 23, 2025 16:09 | July 9, 2025 08:00 | July 9, 2025 16:00 | Perpanjangan waktu menunggu NO dari WB |
| 6 | June 19, 2025 16:13 | July 3, 2025 09:00 | July 3, 2025 12:00 | Dikarenakan perpanjangan waktu negosiasi |
| 7 | June 17, 2025 15:31 | July 2, 2025 12:05 | July 2, 2025 16:00 | Dikarenakan perpanjangan waktu negosiasi |
| 8 | June 3, 2025 10:08 | June 30, 2025 12:05 | June 30, 2025 16:00 | Dikarenakan menunggu NOL dari WB |
| 9 | May 2, 2025 10:53 | June 24, 2025 12:05 | June 24, 2025 16:00 | Dikarenakan Adanya Amandemen TOR |
| 10 | April 23, 2025 16:04 | June 18, 2025 08:00 | June 19, 2025 16:00 | Menunggu NO WB untuk shortlist dan dokumen RFP |
| 11 | March 21, 2025 21:58 | June 13, 2025 10:00 | June 16, 2025 10:00 | Catatan Dari WB untuk perpanjang pengumuman dan EOI |