Schedule Change History
Stage : Combined Evaluation
| # | Edit Date | Original Schedule | Description | |
| Start | Until | |||
| 1 | June 12, 2026 12:21 | June 12, 2026 09:04 | June 12, 2026 12:00 | Perubahan jadwal dikarenakan sudah input financial proposals |
| 2 | June 11, 2026 17:30 | June 15, 2026 08:00 | June 17, 2026 14:00 | Perubahan jadwal dikarenakan sudah input financial proposals |
| 3 | June 2, 2026 17:36 | April 23, 2026 13:05 | April 23, 2026 14:00 | Perpanjangan pemasukan REOI dikarenakan Perubahan Persyaratan REOI |
| 4 | February 6, 2026 16:02 | April 20, 2026 13:00 | April 20, 2026 14:00 | Perpanjang waktu menunggu No Objection WB |
| 5 | January 12, 2026 15:43 | March 16, 2026 13:00 | March 16, 2026 14:00 | Perpanjangan pemasukan REOI dikarenakan Perubahan Persyaratan REOI |
| 6 | December 1, 2025 14:11 | March 9, 2026 13:05 | March 10, 2026 14:00 | Perpanjangan pemasukan REOI dikarenakan Perubahan Persyaratan REOI |