Schedule Change History
Stage : Contract Signing
#Edit DateOriginal ScheduleDescription
StartUntil
1August 7, 2026 10:34July 17, 2026 08:00July 20, 2026 16:00Perubahan jadwal dikarenakan telah mendapatkan NOL dari WB
2June 11, 2026 17:30July 7, 2026 14:01July 9, 2026 16:00Perubahan jadwal dikarenakan sudah input financial proposals
3June 2, 2026 17:36May 18, 2026 08:00May 19, 2026 16:00Perpanjangan pemasukan REOI dikarenakan Perubahan Persyaratan REOI
4February 6, 2026 16:02May 13, 2026 15:10May 18, 2026 16:00Perpanjang waktu menunggu No Objection WB
5January 12, 2026 15:43April 24, 2026 09:00April 28, 2026 15:00Perpanjangan pemasukan REOI dikarenakan Perubahan Persyaratan REOI
6December 1, 2025 14:11April 17, 2026 09:00April 20, 2026 16:00Perpanjangan pemasukan REOI dikarenakan Perubahan Persyaratan REOI