#Edit DateOriginal ScheduleDescription
StartUntil
1February 24, 2026 15:38February 11, 2026 10:01March 6, 2026 13:00Perpanjang waktu menunggu No Objection WB
2February 6, 2026 16:21February 6, 2026 10:01March 3, 2026 13:00Perpanjang waktu menunggu No Objection WB
3January 12, 2026 16:17January 13, 2026 13:01February 6, 2026 13:00Perpanjangan waktu untuk reviu Itjen
4December 19, 2026 14:05January 8, 2026 13:01April 16, 2026 08:01Perpanjangan pemasukan REOI dikarenakan Perubahan Persyaratan REOI