Schedule Change History
Stage : Evaluation of Financial Proposals
| # | Edit Date | Original Schedule | Description | |
| Start | Until | |||
| 1 | June 11, 2026 17:50 | June 9, 2026 09:05 | June 15, 2026 16:00 | Perpanjang waktu menunggu No Objection WB |
| 2 | June 2, 2026 17:41 | April 16, 2026 15:05 | April 23, 2026 13:00 | Perpanjang waktu menunggu No Objection WB |
| 3 | February 6, 2026 16:21 | April 13, 2026 15:05 | April 20, 2026 13:00 | Perpanjang waktu menunggu No Objection WB |
| 4 | January 12, 2026 16:17 | March 9, 2026 14:05 | March 16, 2026 13:00 | Perpanjangan waktu untuk reviu Itjen |
| 5 | December 1, 2025 14:05 | February 27, 2026 14:05 | March 9, 2026 13:00 | Perpanjangan pemasukan REOI dikarenakan Perubahan Persyaratan REOI |