Schedule Change History
Stage : Opening of Tech Proposal
| # | Edit Date | Original Schedule | Description | |
| Start | Until | |||
| 1 | February 26, 2026 10:35 | April 14, 2026 12:01 | April 14, 2026 13:59 | The EOI evaluation is still in progress |
| 2 | February 10, 2026 14:01 | April 6, 2026 12:01 | April 6, 2026 13:59 | The procurement working group has not yet completed the EOI evaluation |
| 3 | January 28, 2026 10:51 | April 1, 2026 13:00 | April 1, 2026 14:00 | The procurement working group has not yet completed the EOI evaluation |
| 4 | January 22, 2026 09:49 | April 1, 2026 00:00 | April 1, 2026 23:59 | The procurement working group has not yet completed the EOI evaluation |
| 5 | January 22, 2026 09:25 | February 26, 2026 13:00 | February 26, 2026 14:00 | The procurement working group has not yet completed the EOI evaluation |