Schedule Change History
Stage : Combined Evaluation
| # | Edit Date | Original Schedule | Description | |
| Start | Until | |||
| 1 | July 10, 2026 15:50 | July 5, 2026 00:00 | July 8, 2026 23:59 | The Evaluation of Financial Proposal is still in progress |
| 2 | July 6, 2026 15:38 | July 5, 2026 00:00 | July 6, 2026 23:59 | The Evaluation of Financial Proposal is still in progress |
| 3 | June 5, 2026 14:17 | June 30, 2026 00:00 | July 1, 2026 23:59 | Waiting for the results of the World Bank’s review of the Evaluation of Technical Proposals |
| 4 | May 25, 2026 15:56 | June 22, 2026 00:00 | June 23, 2026 23:59 | Waiting for the results of the World Bank’s review of the Evaluation of Technical Proposals |
| 5 | February 26, 2026 10:35 | May 29, 2026 00:00 | May 29, 2026 23:59 | The EOI evaluation is still in progress |
| 6 | January 22, 2026 09:25 | May 18, 2026 00:00 | May 20, 2026 23:59 | The procurement working group has not yet completed the EOI evaluation |