Schedule Change History
Stage : Contract Signing
#Edit DateOriginal ScheduleDescription
StartUntil
1October 16, 2026 15:56November 4, 2026 00:00November 12, 2026 23:59The Contract Negotiation is still in progress
2October 9, 2026 10:05October 28, 2026 00:00November 5, 2026 23:59The Contract Negotiation is still in progress
3October 2, 2026 10:34October 21, 2026 00:00October 29, 2026 23:59The Contract Negotiation is still in progress
4September 25, 2026 09:15October 14, 2026 00:00October 22, 2026 23:59The Contract Negotiation is still in progress
5September 18, 2026 12:43October 7, 2026 00:00October 15, 2026 23:59The Contract Negotiation is still in progress
6September 11, 2026 10:20September 30, 2026 00:00October 8, 2026 23:59The Contract Negotiation is still in progress
7September 4, 2026 15:07September 22, 2026 00:00September 30, 2026 23:59The Contract Negotiation is still in progress
8August 12, 2026 13:04September 15, 2026 00:00September 23, 2026 23:59The Contract Negotiation is still in progress
9August 7, 2026 15:46September 10, 2026 00:00September 18, 2026 23:59The Contract Negotiation is still in progress
10August 3, 2026 15:31August 20, 2026 00:00August 31, 2026 23:59The Contract Negotiation is still in progress
11July 10, 2026 15:50August 13, 2026 00:00August 24, 2026 23:59The Evaluation of Financial Proposal is still in progress
12July 6, 2026 15:38August 6, 2026 00:00August 14, 2026 23:59The Evaluation of Financial Proposal is still in progress
13June 5, 2026 14:17August 3, 2026 00:00August 11, 2026 23:59Waiting for the results of the World Bank’s review of the Evaluation of Technical Proposals
14May 25, 2026 15:56July 24, 2026 00:00July 31, 2026 23:59Waiting for the results of the World Bank’s review of the Evaluation of Technical Proposals
15February 26, 2026 10:35July 8, 2026 00:00July 17, 2026 23:59The EOI evaluation is still in progress
16January 22, 2026 09:25July 1, 2026 00:00July 10, 2026 23:59The procurement working group has not yet completed the EOI evaluation