Schedule Change History
Stage : Clarification Request Period
#Edit DateOriginal ScheduleDescription
StartUntil
1July 16, 2026 13:58June 17, 2026 15:01July 9, 2026 15:00Schedule revised to comply with the IsDB RFP timeline
2June 30, 2026 13:50June 17, 2026 15:01June 24, 2026 15:00Schedule revised to comply with the IsDB RFP timeline
3June 12, 2026 09:54April 20, 2026 15:01April 24, 2026 15:00Waiting for No Objection from the IsDB regarding the RFP document
4March 31, 2026 11:17March 12, 2026 15:01March 25, 2026 15:00Waiting for No Objection from the IsDB regarding the RFP document
5March 2, 2026 11:37February 25, 2026 15:01March 3, 2026 15:00Shortlist still under review by ISDB