Schedule Change History
Stage : Contract Signing
| # | Edit Date | Original Schedule | Description | |
| Start | Until | |||
| 1 | June 30, 2026 13:50 | October 12, 2026 08:00 | October 14, 2026 16:00 | Schedule revised to comply with the IsDB RFP timeline |
| 2 | June 12, 2026 09:54 | August 14, 2026 08:00 | August 19, 2026 16:00 | Waiting for No Objection from the IsDB regarding the RFP document |
| 3 | March 31, 2026 11:17 | July 16, 2026 08:00 | July 20, 2026 16:00 | Waiting for No Objection from the IsDB regarding the RFP document |
| 4 | March 2, 2026 11:37 | June 30, 2026 08:00 | July 2, 2026 16:00 | Shortlist still under review by ISDB |