Schedule Change History
Stage : Contract Signing
#Edit DateOriginal ScheduleDescription
StartUntil
1June 30, 2026 13:50October 12, 2026 08:00October 14, 2026 16:00Schedule revised to comply with the IsDB RFP timeline
2June 12, 2026 09:54August 14, 2026 08:00August 19, 2026 16:00Waiting for No Objection from the IsDB regarding the RFP document
3March 31, 2026 11:17July 16, 2026 08:00July 20, 2026 16:00Waiting for No Objection from the IsDB regarding the RFP document
4March 2, 2026 11:37June 30, 2026 08:00July 2, 2026 16:00Shortlist still under review by ISDB