Schedule Change History
Stage : Contract Signing
| # | Edit Date | Original Schedule | Description | |
| Start | Until | |||
| 1 | September 18, 2026 07:48 | October 1, 2026 08:00 | October 14, 2026 16:00 | additional time for F. Evaluation |
| 2 | August 18, 2026 13:03 | August 12, 2026 08:00 | August 19, 2026 16:00 | additional time for M. Evaluation |
| 3 | June 19, 2026 14:41 | August 1, 2026 08:00 | August 14, 2026 16:00 | additional time for Evaluation of Technical Proposals |
| 4 | May 11, 2026 11:08 | June 15, 2026 08:00 | June 19, 2026 16:00 | additional time for Evaluation of Technical Proposals |