1September 2, 2026 18:04September 18, 2026 10:00September 18, 2026 13:00The Evaluation of Technical Proposals is still in progress
2August 13, 2026 15:18September 14, 2026 10:00September 14, 2026 13:00The Evaluation of Technical Proposals is still in progress
3August 6, 2026 16:35September 7, 2026 10:00September 7, 2026 13:00The Evaluation of Technical Proposals is still in progress
4July 30, 2026 15:55August 31, 2026 10:00August 31, 2026 13:00The Evaluation of Technical Proposals is still in progress
5July 23, 2026 13:36August 21, 2026 10:00August 21, 2026 13:00The Evaluation of Technical Proposals is still in progress
6July 16, 2026 14:29August 13, 2026 10:00August 13, 2026 13:00The Evaluation of Technical Proposals is still in progress
7July 9, 2026 13:35August 6, 2026 10:00August 6, 2026 13:00TheEvaluation of Technical Proposals is still in progress
8April 24, 2026 11:25July 23, 2026 13:00July 23, 2026 23:59The EOI evaluation is still in progress
9April 10, 2026 09:41July 10, 2026 13:00July 10, 2026 23:59The EOI evaluation is still in progress
10March 13, 2026 12:19July 3, 2026 13:00July 3, 2026 23:59The EOI evaluation is still in progress
11February 27, 2026 14:04June 17, 2026 13:00June 17, 2026 23:59The EOI evaluation is still in progress