Schedule Change History
Stage : Opening of Financial Proposals
#Edit DateOriginal ScheduleDescription
StartUntil
1September 22, 2026 14:39October 14, 2026 10:00October 14, 2026 14:00Technical Evaluation Report has secured No Objection
2September 21, 2026 08:36October 7, 2026 10:00October 7, 2026 14:00The Evaluation of Technical Proposals is still in progress
3September 14, 2026 08:56September 30, 2026 10:00September 30, 2026 14:00The Evaluation of Technical Proposals is still in progress
4September 7, 2026 10:55September 23, 2026 10:00September 23, 2026 14:00The Evaluation of Technical Proposals is still in progress
5August 31, 2026 09:11September 16, 2026 10:00September 16, 2026 14:00The Evaluation of Technical Proposals is still in progress
6July 28, 2026 12:37September 10, 2026 10:00September 10, 2026 14:00Schedule revised due to the RFP Amendment and WB approval process
7June 12, 2026 08:46September 4, 2026 10:00September 4, 2026 14:00The EOI evaluation is still in progress
8June 5, 2026 08:58August 31, 2026 10:00August 31, 2026 14:00The EOI evaluation is still in progress
9May 22, 2026 08:56August 26, 2026 00:00August 26, 2026 23:59The EOI evaluation is still in progress
10April 28, 2026 14:04July 24, 2026 00:00July 24, 2026 23:59The EOI evaluation is still in progress