Schedule Change History
Stage : Contract Signing
#Edit DateOriginal ScheduleDescription
StartUntil
1October 12, 2026 10:54November 13, 2026 00:00November 23, 2026 23:59The Evaluation of Financial Proposals is still in progress
2September 22, 2026 14:39November 20, 2026 00:00November 30, 2026 23:59Technical Evaluation Report has secured No Objection
3September 21, 2026 08:36November 13, 2026 00:00November 23, 2026 23:59The Evaluation of Technical Proposals is still in progress
4September 14, 2026 08:56November 6, 2026 00:00November 16, 2026 23:59The Evaluation of Technical Proposals is still in progress
5September 7, 2026 10:55October 30, 2026 00:00November 9, 2026 23:59The Evaluation of Technical Proposals is still in progress
6August 31, 2026 09:11October 23, 2026 00:00November 2, 2026 23:59The Evaluation of Technical Proposals is still in progress
7July 28, 2026 12:37October 19, 2026 00:00October 27, 2026 23:59Schedule revised due to the RFP Amendment and WB approval processSchedule revised due to the RFP Amendment and WB approval process
8June 12, 2026 08:46October 13, 2026 00:00October 21, 2026 23:59The EOI evaluation is still in progress
9June 5, 2026 08:58October 12, 2026 00:00October 20, 2026 23:59The EOI evaluation is still in progress
10May 22, 2026 08:56October 2, 2026 00:00October 12, 2026 23:59The EOI evaluation is still in progress
11April 28, 2026 14:04September 6, 2026 00:00September 16, 2026 23:59The EOI evaluation is still in progress