Schedule Change History
Stage : Shortlist Announcement and Issuance of Request for Proposal
#Edit DateOriginal ScheduleDescription
StartUntil
1October 12, 2026 11:59October 2, 2026 08:00October 2, 2026 16:00The selection working group requires additional time to conduct the evaluation.
2September 23, 2026 10:20September 18, 2026 08:00September 18, 2026 10:00The selection working group requires additional time to conduct the evaluation.
3August 31, 2026 19:48September 1, 2026 08:00September 1, 2026 10:00The selection working group requires additional time to conduct the evaluation.
4August 20, 2026 15:58August 20, 2026 08:00August 20, 2026 16:00The selection working group requires additional time to conduct the evaluation.
5August 14, 2026 09:19August 14, 2026 08:00August 14, 2026 23:59The selection working group requires additional time to conduct the evaluation.